A follow-up review meeting was conducted on Tuesday, at the minister’s office, followed by a site inspection. Officials reported that the project has progressed by 10% in the past month, bringing total completion to 45%. The contractor has erected the long-pending LG2 structure, facilitating the faster installation of segments. Three spans have been completed with 35 segment erections from LG1.
Debris and waste materials under the flyover have been cleared to improve traffic flow, while footpath and roadside drainage work is ongoing. Ramalinga Reddy has instructed BBMP engineers and the contractor to complete the project by the end of the year.
The latest site inspection was conducted with BBMP Special Commissioner Avinash IAS, BBMP Chief Engineer Lokesh, contractor Raghunath Naidu, and local representatives, including Rajendra Babu, Raghu, Pillappa, Goverdhan Reddy, Nithin, Sathya, and Shetty, along with other residents.